検索結果 3 件

デジタル記事
2003-12九州大学工学紀要63 4p.203-210
インターネットで読める全国の図書館
  • 要約等...dule operation for whole large ch......ical plant. In the case of polyme......ization plant, the plant operatio......divide to some blocks, which are production block, store block, and so on. The production block is scheduled t......ction cost. On the other hand, the store block is scheduled to operate the production block using feasible scheduling. The following features make the store block scheduling difficult. (1) The product must b......continuum. (2) The product is han......currently. (3) The capacities of queues for intermediates ......per bound. (4) The operations are......y started when the operations can be started. (5...
  • 件名Just in time Hybrid scheduling Scheduling system Silo system Systems engineering
デジタル記事
Takeda, Kazuhiro, Furuyashiki, Minoru, 柘植, 義文, 松山, 久義九州大学大学院工学研究院2003-12九州大学工学紀要63 4p.203-210
インターネットで読める全国の図書館
  • 件名Just in time Hybrid scheduling Scheduling system Silo system Systems engineering
  • 関連情報Memoirs of the Faculty of Engineering, Kyush...
記事
2003-12九州大学工学紀要63 4p.203-210
全国の図書館
  • 要約等...dule operation for whole large ch......ical plant. In the case of polyme......ization plant, the plant operatio......divide to some blocks, which are production block, store block, and so on. The production block is scheduled t......ction cost. On the other hand, the store block is scheduled to operate the production block using feasible scheduling. The following features make the store block scheduling difficult. (1) The product must b......continuum. (2) The product is han......currently. (3) The capacities of queues for intermediates ......per bound. (4) The operations are......y started when the operations can be started. (5...
  • 件名Just in time Hybrid scheduling Scheduling system Silo system Systems engineering

検索結果は以上です。